27th February 2020

Cornwall energy recovery centre operational update (27 February 2020)

Western Power Distribution completed its inspection and clearance of the power export area at the Cornwall energy recovery centre and these works enabled re-synchronisation to the National Grid and re-start of electricity export on Saturday, 22 February 2020.

Specialist roof contractors completed works to remove and secure the damaged section of the roof. Inspections and removal of any insulation materials from the surrounded area have also been undertaken.

Waste deliveries and processing have been unaffected throughout the period of very windy weather and continue as normal.